LBB Group provided a team of pipe welders, pipe fitters, riggers, project management, supervisors, and QC personnel to install double-wall diesel fuel pipes for the complete generator yard diesel fuel supply system.
Details
The assignment duration was 6 months.
There were zero accidents.
4,000 dia-inches of site welds were completed using methods 141 and 111.
1 km of DN150-80 pipes were installed.
Installation, documentation, NDT, and QC were carried out according to the EN 13480 standard and PED regulations.